NYCDDC – HWPEDSF5
Multi-Site Pedestrian Safety Improvement at Various Locations
JED Engineering was retained as a sub consultant to provide Construction Management and Post-Construction services in accordance with task orders issued by the commissioner. Services to be provided shall include without limitation inspection, management, coordination and administration of the project, so that the required construction work is properly executed and completed in a timely fashion.
Project Area 1: Brooklyn – NE Corner of Washington Avenue and Lincoln Road Sheeting for Utilities Relocation for Water Main Installation
Project Area 2: Queens – SW Corner of Utopia Parkway and Station Road Wing Back for Chute Connection for Catch Basin
Contract cost: $15.8M
Status: Ongoing; to be completed June 1, 2024